16th Hole Upgrade

Temporary cart path behind the 16th

On Monday 27 June staff and contractors will be starting the earth works to remove the cart path from the 16th hole
(Weather permitting)

The scope of the work is as follows –

Importing and shaping 400 cubic meters of fill

Installation of new Drainage

Installation of new irrigation

Installation of turf to the reconstructed area

Maintenance of new turf

Course changes –

The 16th hole will be closed until the 21st July 2022

The 7th hole will be played twice, once as the 7th and once as the 16th

During this period a temporary cart path will be marked with star pickets and red and white tape allowing golfers to move safely between the 7th hole and the 8th tee and on the back nine the 16th green and the 17th tee

Golfers will be required to follow safety instructions from staff and contractors at all times